Alex Wong 👤 Member for 23 years 4 months

A plan value cannot change if the activity is already finished



And some planning condition is require in order to have the EV display correctly.



Ie. Actuals $ and Actual Hrs need to more than 0 in order to progress the activity.



You have to be careful with reverse a completed activity.

Suggest you copy the project and play a little bit prior to actually change the completed status