Transfering schedules from P5.0 to P3

R
Ronald Winter 👤 Member for 23 years 5 months

P5 does not support “Interruptible Activities” while P3 does. Change your P3 setting to “Continuous Activities” to make them match. If other durations do not match, then you will need to be more specific on activity types and resource definitions for us to help you further.



The way to ‘cure’ the calendar problem is to copy your P3 schedule to a second schedule (using P3 Project Utilities / Copy) and use the copy. This will clean-up anything that slipped-by in the conversion process. Report the error to Primavera and maybe they will fix it in time for their next yearly version. Good luck!