About Progress Override

E
efren labay 👤 Member for 19 years 5 months
F
Ferdinand Fincalero, PMP 👤 Member for 17 years 10 months

Hello Efren,



Progress override will indeed neglect the critical and near critical path of the program because when you schedule the program it suggests that the started activity/ies be finished as per the pre-programmed duration without minding the completion of its predecessor activity/ies.



Truly, if there is a lot of project delay, with the retained logic scheduling, your program will always be blown out of its completion period. Nevertheless, it shows the realistic status of the project. Re-scheduling effort is just a pain-in-the-ass on the planner’s part.



Utlizing the progress override scheduling will in a way save a bit of your time in re-scheduling as the program somehow sticks near to its completion period with less duration for adjustment to work on. One thing that I do to go around with the forced advanced completion of activities is that I am changing the predecessor relationship from FS to FF (not of course if it is already FF) and put some +lag if seen to be unrealistic in the program.



Simply sharing.



Ferdinand

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts