please help, resources quantities not behaving as usual
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Do you mean you got no more problem? Your question is not very clear to me to be honest.
It seems that you are working with a resource-loaded program complete with units and costs. Whats the common unit that you used by the way? When youre running the schedule, do you use resource units as the weighting factor? Do you link percent complete and remaining duration?
When you load your resources, I believe that you need to specify the "units per day". Are these units freezed?
please give some specifics
thanks for the reply Anoon but the aucost rules and the summarization options of both are consitent.
check the following: Autocost Rules; Summarization (are they consistent?); have you made the target before any updates?