please help, resources quantities not behaving as usual

A
Anoon Iimos 👤 Member for 19 years 8 months

Do you mean you got no more problem? Your question is not very clear to me to be honest.



It seems that you are working with a resource-loaded program complete with units and costs. What’s the common unit that you used by the way? When you’re running the schedule, do you use resource units as the weighting factor? Do you link percent complete and remaining duration?



When you load your resources, I believe that you need to specify the "units per day". Are these units freezed?



please give some specifics

K
Keyel Isorena 👤 Member for 19 years 7 months

thanks for the reply Anoon but the aucost rules and the summarization options of both are consitent.

A
Anoon Iimos 👤 Member for 19 years 8 months

check the following: Autocost Rules; Summarization (are they consistent?); have you made the target before any updates?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts