planning unit is in hours and not days... thanks for pointing that out, cos i forgot to mention it earlier...
Bro;
Just please check your calendar. You are in days duration that is why when you put your actual start same as finish the duration will of course be 0. Please remember that your activity is a task type, so it needs a duration to show.
I just realised it didnt post properly;
Sometimes when I import progress into P3 say in the order below;
Activity Id = AB1000
Percentage = 100%
Actual Start = 23/07/08
Actual Finish = 23/07/08
P3 stores the Actual start and finish dates in the order below;
Actual Start = 23JUL08 00:00A
Actual Finish = 22JUL08 23:59A
Hence making the actual duration 0; has anyone faced this challenge before? Please share how you dealt with it... Thanks...