Activity cannot finish until another - zero float
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Two ways to try:-
1. Activity A 20days FF to Activity B 2 days then reschedule changing Schedule Durations option from Contigous to Interruptible and back (found in Tools, Schedule, Options). No percentage option in P3 but you could put -10 days lag on the FF.
2. Activity C 10 days FS to Activity D 10 days and Activity E 2 days with FS between E and D. Put Zero free float constraint on E.
No a big fan of FF so I tend to use method 2 and define what needs to happen before E is required and then what can happen once it has arrived.
HTH
Vladimir
Can you please elobrate on " no earlier than"?
Also the schedule im putting together doesnt have resource contraints just time contraints. Does this help?
Is there a way to get P3 to behave to get JIT?
It is not supported if resources are limited.
All dependencies used in Primavera software are of "no earlier than" type.
The dependencies you need (JIT) are called "strong dependencies" in Spider Project software.