Link Between Excel & P3
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Ravi/Paul,
I appreciate your help. Thanking you very much indeed.
Cheers
Mustafa
Mustafa,
I Doubt. U can do update P3 and then it will get automatically changed in excel file. For tat u can use pervasive ODBC Drivers.
But, u need to do double handling, if u want data to be updated from execel to P3. Pauls article will explain u in detail about the linking of database between Excel and P3, but requires double handling.
Cheers,
Ravi
There is an article on my web site under technical articles that may help you and the drivers may be downloaded from my software section.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Ravi,
Thanks, but this is still double handling. As you said this is to easy. I am talking about having the excel spread sheet somewhere in the network. As soon as lets say in my case offshore construction super updates the percentage in excel, it automatically mirrors in primavera percentage column.
Thanks in advance
Use Import / Export.
Go to tools --> Project Utilities --> Export.
Its very easy and self-explanatory
The only thing to look out is that excel extension will be Wk1 here and not xls.
Also, import / export will work only for MS Excel 2003 and not 2007.
Export will take necessary activties to excel, while import will bring it back those activities from excel to P3 after updating.
:-)
Ravi