RESOURCE PLANNING
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Shrikant,
a) create resources in Data, Resources
b) open the activity form at the bottom of the scree, then click the RES button to open the Resource sub-form
c) select the 1st activity to which assign a ressource
d) click in the 1st avaliable column in the RES sub-form, select the resource from the drop-down list, enter either Budgeted Quantity or Units per Day
....
Regards,
Alexandre