Sure track resource profile
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
if i understand the question right i suggest dividing the activity into parts where you use the crane and others where you dont . use split opions of primavera , that should sort out the dilemma. use the crane as resouce. as for the excavated dirt you should also assign the excavator as a resource and use original quantaty as the amount of dirt you have to excavate. other than that up date regularly with the amount of cubic meters as you see fit. in primavera that is very feasable.
Wasi
I’m going to assume that it works the same as in P3 (long time since I used Suretrac)
1+2+3; P3 stores resource quantities ("Budgeted qty") as an absolute value for the activity, rather than a qty per time period. Thus, if your crane will be 100% occupied for the whole of the activity length then the budgeted qty you need to enter is the same as the duration of the activity. A short cut is to enter "1" in the "Units per time period" box, which will then calcualte the overall value for the activity. Sadly, if you change the duration of the activity, P3 will not update the budgeted qty figuring that the crane is still needed at 100% but will use the absolute value and recalculate the qty per time period instead. This is a pain but such is life and it is what you would want it to do most of the tim, it’s just a shame that you can’t check a "duration driven" box in the resource window.
4; you can filter to show only the activities with the resource on that you want to see. However, if you have more than one ersource on an activity, the other resource will show up aswell. On the resource curve at the bottom, you can specify that you only want to see a specific resource (or rang of resources)
5; erm. no, I dont think so (assuming I understand your Q) P3 sees a resource as a resource. You can apply cost codes, which would be another way of splitting them up.