Thanks Ronald, it works.
Gilbert,
Before you create your XER file, first open the schedule and run Administration / Purge Deletes. You XER file is probably full of unused information. Good luck!
your topic and your content confuse me.
1. topic: import an XER (from P5.0) into MS Project
The step is export P5 project into MS Project MPP format and open the MPP on MS project
2. content: import MPX to MS Project.
It is not P5 related. Just open the MPX on MS project directly rather import
btw, it is not P3 related, pleae post the question in "P3, P3e/c, Contractor" forum. Thanks in advance