exporting p3 to p5 schedule resources.

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Kevin,



on the documentation CD you can find a manual "P3toPrimavera_v50.pdf", Chapter 3. This I experienced quite reliable.

I use a special P5-database for import.

After import I clean up codes and resources --> then export to xer-format and import into production-database.

Good luck!

Dieter