duration calculation in p3& p5
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
hi
John
Thanks for your help it solved my problem.
Thanks PP
Cheers
Mangesh
Mangesh
This is only a guess but check it out.
I assume your planning unit in P3 is Days. In P5 the planning unit is always hours, but appears as days. You will need to check the hours/day in Admin|Admin Preferences|Time Periods. This deterimnes the calculation for hours per day etc.
You may need to change the duration, then change it back, for the duration to be re-calculated.
Hope this helps.