Job Cards from Plan

M
Marcel van der Leij 👤 Member for 22 years

On a previous project I exported the activity data with a "1-week look-ahead filter" to Excel/Access. From there on you can add fields for actual ressources/manhours used, delays encountered etc. By using Access reports your printing possibilities are virtually unlimited.

The intrinsic advantage of the jobcards of course is the organized and disciplined progress reporting (once you have educated the individuals involved!)

In addition you end up with a database containing all the project history linked to the Primavera activities. The forensic schedulers loved it!



Cheers, Marcel

A
Anoon Iimos 👤 Member for 19 years 8 months

i guess yes, but that would depend on the tasks, i.e. descriptions and durations; maybe you need your job cards daily, then you’ll need lots of details as well

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts