Marked boxes on PERT View
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
I know its strange but this is the way I received the schedule...
Anyhow, those activities have constraints...
How can there be % complete without start, anyway I hope you have now fixed the problem.
Regards,
Ashraf
Actually, there is no start date but there is % complete greater than "0".
Thanks anyway...
Check Again,
Single diagonal line is for started activites. You must have put Actual start date for these.
Regards,
Ashraf
No, only one diagonal through the box, plus I only have activities not started....
Nicolas,
By striped if you mean X crossed , then it is the completed activites.
Regards,
Ashraf