Production Rate & Crew Structure

M
Mike Testro 👤 Member for 20 years 5 months

Hi Osama



The problem is that anyone can list a set of outputs on PP that are complete rubbish.



Every project has its own distinct set of circumstances that require different production rates.



The answer is to go to your estimator and ask what he considered to be the best production rates for the project.



If he doesn’t know then you may just as well make them up yourself.



Best regards



Mike Testro

O
Osama Warid 👤 Member for 19 years 3 months

Greetings for all

Everybody askfor productivity rate sheets could we find in the site an area to down load a file including these productivity rates instead of sending it to specified e-mail for single person.

if this area are available can all the people get the benefit from it

Regards,

D
D Artagnan 👤 Member for 17 years 8 months

hi samer, thanks.



i tried to contact them two weeks but still in vain.



thanks for the site. when i did my search i get some error.



thanks again.

M
Mike Testro 👤 Member for 20 years 5 months

Hi All



Make sure that no document is copyright before sharing.



Best regards



Mike Testro

D
D Artagnan 👤 Member for 17 years 8 months

hey IC, i have been looking for this manual. Can you please send me a pdf of this. How old is it? coz i am making a database for productivity rates and the manpower requirements.



please...


Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts