Resources on Summary Bars
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
David,
The easy way is to insert an activity and change the type to WBS instead of task and then schedule, there is no need for any links and this will be similar to the summary bar and you can assign resources to this activity with your lag and duration for each resource as normal.
Kind Regards
Mohamed
try and use a hammock activity.
start-start to first activity in schedule,
finish-finish to last activity in schedule.
activity type: hammock.
it is good practice to link the start and ends to milestones.
Gün.