how can i adjust project target duration?

J
Jason Smith 👤 Member for 19 years 6 months

If you choose to use the update target feature I would save a back up first. Make sure that you choose only the items that you want to have updated on the target file. It is easy to update more than you wanted to if you are not careful.

E
Eric EVRARD 👤 Member for 19 years 6 months

Hello,

A project target is only another project recorded in your P3 files and then shown on your layout when selected.

You need to open the project you use as a target, change whatever you want and it will appear with its modifications on the project you use.

A
Alex Wong 👤 Member for 23 years 4 months

read the tutorial of how to create a schedule... that will help


Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts