remainging duration

T
Tahir Naseem PMP, CCE 👤 Member for 19 years 7 months

Dear Mohammad

I already try this option but not working. Thanks for reply. I found the mistake there is some mistake in logic that why the remaining duration was calculate after the FS of predessor activity where as this should be FF with a counted lag.

Thanks again for quick reply.

Regard

Tahir

M
Mohamed Thabet 👤 Member for 19 years 8 months

Hi,



To update separately the remaining duration & the activity % comp. Just uncheck from the auto cost rule "Link remaining duration & schedule percent complete"



But then you have to update remaining duration for all the schedule activities manually.



Regards,



Moe