Dear Mohammad
I already try this option but not working. Thanks for reply. I found the mistake there is some mistake in logic that why the remaining duration was calculate after the FS of predessor activity where as this should be FF with a counted lag.
Thanks again for quick reply.
Regard
Tahir
Hi,
To update separately the remaining duration & the activity % comp. Just uncheck from the auto cost rule "Link remaining duration & schedule percent complete"
But then you have to update remaining duration for all the schedule activities manually.
Regards,
Moe