Physical progress

P
Paul Harris 👤 Member for 25 years 2 months

Alexandre



I usually use the % Complete for physical progress.



I then unlink all the auto cost rules and then I am able to enter actual hours and costs to date and estimates of hours and costs to go.



I create three other Custom Data Items. % Duration, % Cost and % Hours which are calculated by Global Change.



One can also use the % Complete (which represents the Physical % Complete) to calculate the cost and hours to complete from the Actual costs and hours, therefore using the actual progress to estimate the remaining progress.



I create two baselines, one without progress and one that I auto status to give me the planned % complete.



The article on my web site Practical Application of Earned Value Performance Measurement Using P3 shows some of the things one can achieve with P3. Look at the last 2 pages.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts