Thanks, Paul
your answer is very useful for me
Alexandre
Alexandre
I usually use the % Complete for physical progress.
I then unlink all the auto cost rules and then I am able to enter actual hours and costs to date and estimates of hours and costs to go.
I create three other Custom Data Items. % Duration, % Cost and % Hours which are calculated by Global Change.
One can also use the % Complete (which represents the Physical % Complete) to calculate the cost and hours to complete from the Actual costs and hours, therefore using the actual progress to estimate the remaining progress.
I create two baselines, one without progress and one that I auto status to give me the planned % complete.
The article on my web site Practical Application of Earned Value Performance Measurement Using P3 shows some of the things one can achieve with P3. Look at the last 2 pages.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting