Importing from MS Project to P3e

D
Davie Ross 👤 Member for 19 years 10 months
D
Davie Ross 👤 Member for 19 years 10 months

Thanks for your help I think the problem is RAM. I have managed to import 5000 activities at a time no problem.

A
Alex Wong 👤 Member for 23 years 4 months

The quick answer is NO



But... you know that is coming...



In P3e, it does drive a lot of resources especially if you use Oracle or SQL server to drive P3e. As a result, the number of importing or exporting is very dependent in the Memory. Both virtual and Physical Memory. My suggestion is you must at least have 2 G memory (RAM) to operate P3e

Ideal case is 4G



(BTW you posted this in the wrong forum topic)



Cheers



Alex

M
Marcio Sampaio 👤 Member for 20 years 7 months

The maximum I did had 15.000 activities.



I think there is no restriction.



Regards.



Marcio Eduardo.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts