Sure Trak dates entering problem

P
Paul Harris 👤 Member for 25 years 2 months

Dear musawar Shaikh



The intension of the software is to calculate the dates for you. When an activity is added the dates will be calculated for you by entering a start date of the project and then adding relationships amongst the activities. You may apply constraints to activities to prevent the tasks before or after dates.



I suggest you read up on the basics of Critical Path planning as a start to understand the basics of software such as SureTrak and then read the manual or a book obtain some training in the software.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts