Work shift query

P
Paul Allen 👤 Member for 20 years 6 months
J
Jaime Linchangco 👤 Member for 24 years 10 months

Hi Paul,



There’s a turnaround for this. Define first your new calendar. In the standard, first define your non-working day which i supposed sunday by assigning 00:00 for both starting and end time. Press OK.



Then, from day 1 of your Project, click that date and press simultaneously "shift" key then scroll down to the Finish date. Since all the days for your Schedule are all highlighted, click the Hours 5 and choose "Nonwork". Then click 6 and choose "Nonwork". Do the same on 15 and 16. Then press OK.



For your activities to start on 7am, specify in your Data Date the hour at "7:00" everytime you Calculate or pressing F9.



That should do.



Cheers!



Jaime

A
Andrew Podolny 👤 Member for 21 years 6 months

Hi Paul,

I think it’s not possible. Probably it’ll be better to create two different calendars reflecting your 1st and 2nd shifts’ working hours and apply this calendars to the particular resources. Then you may use both types of calendars in one activity (independent).

Best regards,

Andrew

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts