P3 SCHEDULE VARIANCE

T
Trevor Lyle 👤 Member for 21 years 11 months
T
Trevor Lyle 👤 Member for 21 years 11 months

Thanks William



I am on vacation at present and will try your suggestion when I return to the office next week.



Thanks again.



Trevor Lyle

W
William Desamero 👤 Member for 20 years 4 months

Hi Trevor,



To clear variances (per activity):



1. check that your remaining duration (RD) is not equal to 0

2. if RD is 0, reset your progress PCT % to 0 (note previous figure)

3. increase your original duration (OD) and enter orig PCT %

4. repeat items 1 & 2 until RD is at least 1

5. click Res (Resources) Tab

6. edit the figure "At Completion" and make it equal to "Budgetted Quantity"

7. Click OK.



Hope this helps.



William

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts