P3ec has two places where dates can go, early dates and planned dates. When you perform a CPM analysis, the calculations go into the early dates section. When you do a resource leveling, the new leveled dates go into the planned dates section. The leveled dates will also go into the early dates section unless you use the option that you asked about. Good luck!
I should have clarified sorry Im talking about P3E 4.0
Thanks