resources managements

A
Amin Sorour 👤 Member for 20 years 4 months
C
Charleston-Joseph Orbe 👤 Member for 20 years 11 months

Hello Amin,



I would suggest go for your idea, experiment a lot, read books and involve in hands on planning using excel, P3, etc. Whatever knowledge you learn, keep on multiplying and improving you understanding of the secrets of planning. Along the way you will meet a master, planning master to guide you to perfection.



It is only then that you will find true meaning to the answers to your questions.



IMHO.



Cheers,



Charlie


R
Raja Izat Raja Ibrahim 👤 Member for 21 years

Hi

1.Yes for preliminary, parallel with that you have to identify the design change request or missing / over looked item which not include.

2.Use total item.

3.Either one could be use, depends on contract requirement.

4.Cost account / cash flow will base on unit rate, which followed by controlling milestone claim or monthly claim.

5.Dont have one, whatever my answer is from experience and actual practice at my company.

6.Not suitable time but u can PM me at anytime.



for further question, if u could tell me which area u are focusing either cost control or Planning Scheduling.



Regards

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts