%plan vs actual progress

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

first you have to create a target schedule from your current schedule, if you already have a baseline/target schedule, make this schedule to be available in the current schedule layout



i.e

Tools->Project utilities->targets and choose the schedule you want to compare.



then only you can get those figures that you wanted to get.......



regarding global change it depends on the availability of row in global field i believe you can use many conditions but use it wisely.

I
Iftikhar Awan P.Eng. 👤 Member for 20 years

Hamid,



It seems like you are undergoing a self-learning process like me. I have also faced problems like these, which pushed me to get help from books.



I would strongly recommend that you read the book "Planning Using Primavera Project Planner" by Paul E. Harris.



I have found his books really helpful in accomplishing essential tasks like comparing actual with target progress.



Good Luck.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts