As-Built Activities in Critical Path

R
Ronald Winter 👤 Member for 23 years 5 months

Any completed activity that is logically included in the current longest path is reported as being on the longest path. To not do so would leave a gap in the longest path. P3 identified this activity while tracing the controlling predecessor back from the last activity in the schedule. P3 stops tracing the controlling predecessors when it reached the last unfinished activity in this chain.



This technique does not allow for the identification of a longest path for completed activities with an internal scheduled start ‘before the data date’ otherwise. Good question!

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts