"Calendar not current"

S
Sajid Balma 👤 Member for 19 years

It is definitely a late input, but for those who encountered the same error message in future, F9 your project and run the report and you won’t have any issues then.

C
Chris Murray 👤 Member for 22 years 3 months

Marcio,



Not sure how but, it is now working.



I think it may have been due to some of the date ranges within the report i.e. before the Project Start date.



Played with that many boxes not suyre exactly how! Not sure if this will help



Chris