Ordinal Dates

M
Marcio Sampaio 👤 Member for 20 years 7 months

Is this the answer??



"This is the way the system is designed. In p3 if the unit is month it does not recognize any unit below so January 06 is one month and it does not recognize 15th or 30th .It is more evident if you plan your project with month as planning unit. The best option is use week in this case (under ordinal dates unit) if you want to be more accurate."



Regards.