EV uses budget from current or target project?

P
Phil Palmer 👤 Member for 23 years 1 month

Vanessa,



I have used this option when after baselining a schedule I have entered unapproved variations into the current schedule, with a budget. I then have the option to establish the earned value based on original scope (Target1) or current scope plus unapproved variations(current). In the real world variations can progress before approval (although again theory tells us this is taboo).



There are a lot of schedules that I have come across as a consultant that have no baselines. I suppose what Primavera is also doing is making allowances for those who do not apply a target.



Regards