Physical % of Completion Vs Schedule % completeion
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hi,
Unlink the remaining duration with %complete from AutoCost rules. Than fill the RD.
Cheers
Hi joseph,
u can play round resource lag, and shift every resources for that activities to 50% elapsed time, so the physical progress will show 0% and Time duration showing 50% or u can put as non working day for that activities for activities for 5 days.
hope this can works...