You would need to create & provide unique activity code for each subcontractor and reflect the same in the program activity id. hence the activity id themselves would help in differentiating the subcontractors when you integrate their programs.
Hi,
you need to develop some procedure for all subcontractor on scheduling,including
name of the project, act ID, codeing structure, resource,how to link tasks from different contractor,level of detail, method of updating...
you need to think about how to update this schedule,you may do this kind of intergation once a week. for a power plant your detail schedule may have more than 50000 tasks. if they are not well organized, you will have big problem when updating them