Bogus EF dates...
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Go to Project Overview > check Project Must Finish By. If you imposed any finish date constraint, remove it and re-calculate the schedule.
Regards.
No, I checked all that.
It turned out to be a topic activity that had a predecessor! I ran the no-topic utility, and organized the schedule in suretrak in outline mode, then outdented everything. Now my RD is driving my EF.
Do you have an Expected Finish constraint posted for that activity?