filter for open ends !?

M
Mary JoAnn 👤 Member for 23 years 3 months
D
DATTATREYA PADHARTHI 👤 Member for 23 years 1 month

It’s somewhat lengthy.

Donot delete activities (E&P) initially. Export all activities (E&P) with successor relationship. You will get construction activities having atleast one Engg/Proc predessor.

Take the successor column & add a temporary activity code (Please add the same code in P3 file).

Import the file in P3 & select activities having this code.

Those Construction activities are the ones without predessor (E&P).

Please note that those activities having Constrn activities as predessor will also appear. (e.g Installation of Equipment will have , 1) delivery of eqpt & 2) foundation of Eqpt as predessor. So take this into consideration.



Regards

Dattatreya Sriniwas

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts