Time Impact Analysis using P3

R
Rashid Iqbal 👤 Member for 21 years 1 month

If you go AACE web site, you can find a large number of articles on this subject. The authors of these articles have also cited numerous court cases as well. You can observe that most of the ’authorities’ have categorized the delays as follows:



Excusable and compensable

Excusable and non-compensable and

Non excusable



You can find their descriptions and the details of the methodologies to be deployed for quantifying and proving causation in the above mentioned articles/web site. For example, the second type would be due to both the parties in parallel networks etc. Though in any case it is fairly a tricky and a contentious issue and would not be as easy as explained in literature.



Regards

Rashid

Z
Zubaer Shariff 👤 Member for 22 years 4 months

After completing as-built schedule, I sugest you compare it with the target schedule, the contractor had (should have) submitted before starting the work.

-Zubaer

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts