Construction Project Control

A
Anand Kulkarni 👤 Member for 21 years 2 months

Imam,





Actually your countries counterparts could give better guide.



But any civil engineering Handbook, Q.S. book will contian the labour productivity.



Or the GR released by the Public works department for the current year does have this information.



Otherwise as a thumb rule in most of the activity a skilled person should do a job of 100 - 125 Sq.fts.per day










M
Mirza Imam Baig 👤 Member for 23 years 1 month

Thanks Anand.



Further can you please advise a few Standard Reference Manuals on Labor out-puts, so that I can quickly refer and estimate the duration of my activities.



Appreciate your help.



Regards,

Imam Baig

A
Anand Kulkarni 👤 Member for 21 years 2 months

Hi Imam,



For any given activity completion resources are material / Manpower & Equipments & they can be tracked on either all the three or on one.



There are standard reference manuals on labour out puts per hour/day in market, or some company’s develop of their own based on the project experience.



Ultimatly updation is based on consumption of the resources for any activity what ever is the resource.

So rest of things are same.



Hope this could get you some help!!



Anand


Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts