Trade Filter

A
Azvi Hanifa 👤 Member for 21 years 8 months
A
Azvi Hanifa 👤 Member for 21 years 8 months

Thanks



Philip



your answer open the thought, but still if you would elaborate with example and how can open the code from the p3 etc will be more helpful



Regards



Azvi


P
Philip Jonker 👤 Member for 21 years 7 months

Hi Azvi,



It is simple, create a resource code for each trade, and add the resources to the program, eg Resource CONC is concrete work, FINI is finishes etc. Then run s-curves for each resource, this will give you what you need.



Regards

R
Ravi Potwar 👤 Member for 21 years 3 months

Hi,

Why you want to export the activity.

You can do from Schedule itself ,Create column Planned % ( Baseline at datadate -Updated % ) Actual% (% completion ) in schedule Itself . Take Print out, If you don’t want Bar chart ,Tick off the Option.

You can summarised this Schedule as report. I don’t think any problem.


G
george stewart 👤 Member for 23 years 7 months

If you set up a new export file, then filter your selection and use the target % complete and actual % complete. run this and you will get the results required.

See Tools, Project Utilities, Export. If you require more help come back

George

A
Azvi Hanifa 👤 Member for 21 years 8 months

Hi



I intent to produce report for each trade progress

exp:

Planned% Actual% Slippage

Earth work ----- ----- ----



Concrete work ----- ------ ----



Finishing work ----- ------ ----



Thanks

R
Raj Maurya 👤 Member for 21 years 10 months

Could you eloborate your question? What exactly you want to do?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts