Weighting in P3 ? How & Where

S
Steven Oliver 👤 Member for 23 years 7 months

Thats what I meant. How are you going to distribute the manhours to produce a baseline to compare the earned value to ?.

S
Samantha McCulloch 👤 Member for 22 years 9 months

Thanks for the assistance Steven, if you’ve some more advice about comparing against the baseline I’d appreciate that also.



Samantha

S
Steven Oliver 👤 Member for 23 years 7 months

It would be possible, if you were to create a 2 custom data items, one to hold the budget value and one to hold the "earned value", then use a global change to multiply % complete for the activity by the 1st CDI and place the result in the 2nd.



Bit of a nut and slegehammer job, but would work.



How do you intend to arrive at your baseline distribution to compare the earned value to ?. Earned Value on its own is just a number.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts