Resource Requirement in P3

M
MK TSE 👤 Member for 24 years 3 months

Q1. Time duration cannot reduce. Only one excavator, complete the activities one by one. Duration of each activity will depends on the production rate.

Q2. If in resource library, stated the upper limit of excavator is 2, then do a schedule and level to the network, over duration may cut down since 2 activities are in progress "parallel"

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts