Baseline Quantities Change

B
Bensouyah Mohamed 👤 Member for 22 years 5 months

to Mr PAUL HARRIS



THANKS A LOT FOR YOUR REPLY



I HAVE BOUGHT YOUR VERY INTERESTING BOOK ABOUT P3 3.0



I FIND IT VERY INTERESTING.





FOR THIS QUESTION . I’ll STUDY YOUR RESPONSE



AND AFTRER GIVE U THE RESULTS



THANKS A LOT



CAN I SEND U BY E-MAIL MY FILE OF PROJECT PLEASE



THANKS A LOT ANOTHER TIME.

P
Paul Harris 👤 Member for 25 years 2 months

A couple of things to look at:



1. One option you will need to understand is found under Tools, Options, Autocost Rules. The Freeze Units per time period should be unchecked and then quantities will not change when durations change.



2. Also you need to check the subtract Actuals from ETC or Actuals Quantities will be added to the At Completion and increase the At Completion value.



Regards



Paul E Harris

www.eh.con.au Eastwood Harris Books

M
MK TSE 👤 Member for 24 years 3 months

have you re-schedule the newtwork after data input?

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts