Paul, I modified your link to work correctly. Please see this post explaining how to add a link correctly.
Bernard Ertl
InterPlan Systems Inc. - Project Management Software, Project Planning Software
to Mr PAUL HARRIS
THANKS A LOT FOR YOUR REPLY
I HAVE BOUGHT YOUR VERY INTERESTING BOOK ABOUT P3 3.0
I FIND IT VERY INTERESTING.
FOR THIS QUESTION . I’ll STUDY YOUR RESPONSE
AND AFTRER GIVE U THE RESULTS
THANKS A LOT
CAN I SEND U BY E-MAIL MY FILE OF PROJECT PLEASE
THANKS A LOT ANOTHER TIME.
A couple of things to look at:
1. One option you will need to understand is found under Tools, Options, Autocost Rules. The Freeze Units per time period should be unchecked and then quantities will not change when durations change.
2. Also you need to check the subtract Actuals from ETC or Actuals Quantities will be added to the At Completion and increase the At Completion value.
Regards
Paul E Harris
www.eh.con.au Eastwood Harris Books
yes , of course
have you re-schedule the newtwork after data input?