Bar Chart & Network (PERT) Finish Dates not Matchi
Forum Sponsor
Top Posters
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
I just try it on my P3 and there are not any discrepancy between the bar chart and the pert data.
As are extrimated once for ever, or until next scheduling.
I used a 7 working days calendar.
Try to see which info are you asking to be shown in pert view.
If You want a copy of this and see how is running on your P3 send me You email.
Did You try to re-set the activity box info in PERT view?
To clarify my point, herebelow is a simple example.
Create a new project with planning unit in weeks, starting on mondays and with a start date of January 5th 2004.
Activity 1 has duration of 2 weeks and is linked with FS to Activity 2 that has a duration of 3 weeks.
The Bar Chart Layout shows Activity 1 finishing on January 18th 2004, and Activity 2 on February 8th, 2004, and both are correct.
Now, if you go to View, PERT, it shows Activity 1 finishing on January 12th 2004, and Activity 2 on February 2nd, 2004, and both are wrong. These 2 finish dates represent the starting dates of the weeks in which these activities end.
Hope my example is clear.
Anybody has an idea what is happening?
Thanks.
please check the start day of the week are same. Project property and report option.