I checked that but only the current estimate is selected. I have got resources loaded on the uncomplete activities too. But it still doesnot show the histograms on the right of the data date!!! Any other suggestions. Thanks
I bet youve selected to show earned value in both resource table and profile. Thats why no value is shown after the data date.
To solve this, select either current estimate or planned value from the display option of the resource profile or resource table.
Jorge
Check, If u have selected right resource(u have used). Also, check if histogram option is checked ON.
there are no resource constraints,a normal ,resourced, linked, updated program. Has it got something to do with the display options of the resource profile? the resource table also shows the same.
Is data input correctly? Any resources constraint been induced? PCT=100% or RD=0?
Please provide more information.