Timescale - how to format to Ordinal Week 0?
Forum Sponsor
Top Posters
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
D1
D2
D3
D4
D5
D6
D7-W1
Like that days going but where you can bring 0 days 0 week?
Thank you to all who have responded to my question. Now I have a clearer picture on Ordinal Date.
Best regards,
CS Ong
I agree with what Mohamed Gebriel mentioned. The Week 0 means nothing.
If your project duration is 60 weeks and you want to show the timescale by ordinal weeks starting by WEEK-0 and ending by WEEK-60 then you will see that your project duration well be 61 weeks. I know that neither you nor your Client wants to show this in the proposal schedule.
Bye then,
Ali Vessali
Gents,
I believe this problems goes back to the concept of planning Primavera uses. Even if we talk about days there is no day "0" in planning. Theoritically Day "0" is a (no duration) breakpoint between Day 1 and the day before. Its just a point not a day. The same is with weeks. The 1st week of your project IS week 1. There is no week "0".
Maybe the alternative is to try and convince the client with this logic way of showing the timscale in your reports. Hope I could have been of help.
Hi there,
Yes, we stand corrected. I will advise the sorry individual who came up with that answer !!!
Regards.
The Planning Planet Team,
Thanks for your kind suggestion BUT still you will not be able to show Week 0.
Best regards,
CS Ong
Hi there Mr Scheduler!
On the same window that you used to select "Ordinal Dates" you should see (at the bottom of the window) two selection choices...
"Units" - to choose weeks, months etc etc and
"Ordinal Start" - to change the start date (calendar days, referencing your ES, EFs). If you adjust this Ordinal Start date you will see that it changes your week numbers.
Hope this helps you.
Kind Regards
The Planning Planet Team