progress vs completion date

Hi Planners,

I am preparing S-Curve for construction project, let's assume the planned progress for the month is 60% and the actual progress is 55%, we are 5% behind. It is not necessary mean that the planned completion date has shifted or should go further?

I think it is not necessary the planned completion date to go further, am I right?

I seriously need your explanation

Regards,

Muataz

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Moutaz,

If the progress is delay, it does not necessary mean that the completion date is being push out or go further unless the delay is coming from the critical path. If the critical path is affected then recovery is needed to come back from the original completion date such as re-sequence the activity or compressed the schedule by addressing the delay and de-risk the critical path. Sometimes it happened that the progress is ahead than plan but overall the schedule is delay because the critical path is being affected by other delayed activities. Investigate, review and analyse your schedule and check where and what is the cause of behind schedule? Is it on the critical path or non-critical activities? Is it the weighthing of the activities or productivity issue?

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts