Planned / Actual % Complete S-Curve

R
Ryan Wheal 👤 Member for 11 years 8 months

Morning all,

 

Just trying to do a very basic planned vs actual percent complete S-Curve.



Any idea how it's done?

 

I just want to show the variations between the two.



Kind regards.

R
Ryan Wheal 👤 Member for 11 years 8 months

I don't want  to show any cost allocation etc, just a basic planned % complete vs actual % complete line over the project duration.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ryan

This is too big a topic for exchange here.

Go to Help and search on Histograms.

Select "Introduction to Histograms" and start from there.

Best regards

Mike Testro

R
Ryan Wheal 👤 Member for 11 years 8 months

Hi Mike,

 

Thanks for your response, but I'm struggling a little here.



Any chance you can help me with a walkthrough of what I'm meant to do?

 

This is the first histogram I've ever done and haven't a clue...



Kind regards,



Ryan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ryan

Asta software will do this for you.

Create a histogram with the selected data.

Right click the histogram and select S-Curve - the graph will be created in Excell.

Best regards

Mike Testro

Forum Sponsor

Top Posters

MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts