Budgeted resources changes everytime i import data

J
Jaco Stadler 👤 Member for 21 years 9 months

Hi Rolyn Transfer Autocost Rule from another Project. (One you are sure that you did not have any problems with)



Also have a look as to earned Value are you using Target Project or Current Project

R
Rolyn Jalea 👤 Member for 22 years

Alex,

the budgeted quantity of some of my activities changes, some have increased and some decreases... there’s no pattern whatsoever. therefore my budgeted cost also changes. This is the first time I’ve encountered such problem like this. and this problem only occurs every time I import data (i.e. AS, AF & PCT).

F
Frank Borcherdt 👤 Member for 25 years 1 month

Rolyn,



I would check your autocost rules (Tools, Optiosn, Autocost).



You mentioned it is cost loaded and you collect AS, AF and PCT. To have the system estimate the actual you will need to have the option checked to Use updated percentage against budget to estimate actual cost (or quantity) to date.



If these are not set and you are not collecting and inputting/importing the actual cost (or quantity) then as you import the AF the RD becomes 0 and forces the CTC and CAC (and QTC/QAC) to zero and you appear to lose those values from the Project.



HTH

A
Alex Wong 👤 Member for 23 years 4 months

Can you please describe a bit more



is your quantity or $ changed

is increase or decrease

how you update your actuals (Import and Export)



cheers



Alex

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts