Gents,
I understood you used the "project must finish date" as a ultimate "wall" for the end of your project. You already found out that projects can be delayed or in other cases activties are still to be planned/executed.
In most cases it is better to leave the PMF date open or at the end of the year (f.i. 31-12-2003) and put a mandatory finish contraint at a "final" milestone. The PMF date puts a limit to (calendar) calculations P3 makes and also the timeframe of the screen and print layout.
So good luck next time!
Ed van der Tak
ARAM Planning Consultants
The Netherlands
Hi! Tara,
Yes, you are correct! I removed the mandatory finish constraint on the Finish Milestone and everything is ok.
Thank you and best regards,
CS Ong
Hi,
The only reason I can think of is you also have finish milestones with Mandatory Finish Constraint or even a Late Finish Constraint.
Please remove this and try rescheduling,this should work.