Ed van der Tak 👤 Member for 24 years 3 months

Gents,



I understood you used the "project must finish date" as a ultimate "wall" for the end of your project. You already found out that projects can be delayed or in other cases activties are still to be planned/executed.



In most cases it is better to leave the PMF date open or at the end of the year (f.i. 31-12-2003) and put a mandatory finish contraint at a "final" milestone. The PMF date puts a limit to (calendar) calculations P3 makes and also the timeframe of the screen and print layout.



So good luck next time!



Ed van der Tak

ARAM Planning Consultants

The Netherlands

P
P3 Scheduler 👤 Member for 24 years 3 months

Hi! Tara,



Yes, you are correct! I removed the mandatory finish constraint on the Finish Milestone and everything is ok.



Thank you and best regards,

CS Ong

T
Tara Muddappa 👤 Member for 23 years 5 months

Hi,



The only reason I can think of is you also have finish milestones with Mandatory Finish Constraint or even a Late Finish Constraint.



Please remove this and try rescheduling,this should work.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts