Calendar problem detected, Your project is too lon

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Scott,



You can do this by making a copy and changing the the planning units there, there is a help topic in P3 that explains it, under "planning units, revising".

However, I have in the past done it by exporting, and manually changing durations and successor lags in excel, by mass editing, according to calendars and then importing. In your instance exporting from the hourly project, and importing to a daily project.This can also be used to check the copy method. The main concern I have about the copy method, is that when you have multiple calenders, that the durations are calculated correctly for the various activity calendars.



Regards



Philip

S
scott aitken 👤 Member for 21 years 10 months

The planning units are actually in Hours, so I think this may be the problem. How do I change these to days?

P
Philip Jonker 👤 Member for 21 years 7 months

Hi Scott,



There is a few posibilities:



P3 has a maximum number of planning units it allows.



Go to file->project overview and check the project start date and the project must finish by date. Should this be longer than the maximum allowable number of planning units it could be your problem. It could also be due to the PSD being set too early. If the project must end by date is set too early move it out.



Other than this check your calendars, both the scheduling and resource calenders.



Regards



Philip


D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

Scott,



The other option you can try is, check your final network’s activities sequence and increase the duration and see whether it reaches the required project completion period.



HTH



Daya

W
Waseem Saber 👤 Member for 21 years 6 months

Hi, Scot.



there is a possiblity that the activites duration do not comply with the end date(correct me if i am wrong)as this happens if the total duration for the activities should show the same or else you can make a constriant for EF, LF for Dec’2008 and i am sure it might help



waseem saber

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

Hello Scott,

I think this is the first time i am hearing about this kind of calendar problem, have u checked your programme with some other machine(where P3 installed). How many calendars did you assign to your projects, check your activity’s calendar where it stops at May 2008.



please brief me further.



Regards



Daya

S
scott aitken 👤 Member for 21 years 10 months

Runs from Jan 2005, want it to go to Dec 2008, currently stops at May 2008.



Units are in days, displyed in months.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts