Activity Code vs WBS field

J
Jorge Taguinod 👤 Member for 22 years 11 months

I think that WBS was developed to help project managers to at least be able summarize large project data. WBS provides only one way to look at the project.



However, with the advent of computerized project management software, PMs dont have to be limited anymore to just one perspective. And P3 uses Activity Codes so that you can slice and dice information in many many ways... by activity codes, project codes, resources, time, float, etc. Imagine if you needed to do this manually?



I would always recommend the use of Activity Codes becauase filtering, grouping and summaryzing, and performing global change is much easier this way... plus the fact that I can view project information in countless perspectives which can be saved in different layouts.



Jorge

Crown Systems (Philippines)

T
Tara Muddappa 👤 Member for 23 years 5 months

hi,



The way I view is to have WBS structured the way you build the Job.On the other hand activity coding gives you ample flexibility to view the reports of your choice.

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts