How to generate Resource Report?

S
Suresh Devarajan 👤 Member for 21 years 11 months

Hi Paul,

The software that I am using is P3 version 3.1. I am still working on the solution.

Thank you,

Suresh

P
Paul Harris 👤 Member for 25 years 2 months

This is the P3 not the P3e/c forum. Which product are you using P3 or a Primavera Enterprise version, you mention the P3e/c forum below, there is a big difference between the two products?



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Book Publishers, Training & Consulting

www.eh.com.au

A
Andrew Podolny 👤 Member for 21 years 6 months

Hi, there!

Try

Tools-->Tabular Reports-->Report Writer...

Select "Resource Control - Detailed By Activity" report and modify it according to your needs.



Best regards,

Andrew

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts